This week we finished the last of our planned repairs at Miller and Miller Boatyard:

·       Replaced Asko Washer.

·       Replaced sound dampening material for 6 kW 

·       Weld repaired, cleaned and painted Balmar alternator belt guard

·       Investigated mystery toggle switch on flybridge – added rocker switches

·       Maretron DSM410 in pilot house and master cabin

·       Stereo – added speakers to pilot house 

·       Tighten port faucet at swim step 

·       Weld repair engine alternator belt guard

·       Add Fusion remote to P/H

·       Replace two stern cleats with low profile or pop-up cleats (Seasmart)

·       Make two stainless cover plates for down rigger

·       Check hydraulic steering pressure

·       Replace 25 kW volt meter on panel (P/H)

·       Check bow thruster wiring for proper connectivity

·       Hailing speaker

·       Added Maretron DCM 100 battery monitor


As we await the new Asko dryer, we are repositioning Raven to Yacht services to complete the last two major items on our list:

    Re-plumb the water maker to a forward location

    Install Hydronic heating system



Down rigger mount


Down rigger all set



 
Polished counter tops